A Commercial High Court in Accra has granted a motion for an interlocutory injunction restraining the government of Ghana from making further monthly payments to ENI Exploration and Production Ghana Limited and its partner, Vitol Upstream Ghana Limited for gas supplied to the state from the Sankofa Field.
The order, issued on Friday, July 12, 2022, specifically restrains the Ghana National Petroleum Corporation (GNPC), Ministries of Energy (MoE) and Finance as third parties, from making any payments whether outstanding or recurrent to the two oil companies pending the determination of an application brought against the three state organs by Springfield Exploration and Production Limited, a wholly-owned Ghanaian Energy company.
According to the ruling, Springfield filed the motion on June 20 2022 seeking the order by the court for GNPC, MoE and MoFeP to make all payments to the Registrar of the Court.
It explained that the action by the Ghanaian energy company is believed to be a sequel to an ongoing legal tussle that has seen Springfield win a judgement to preserve part of the proceeds from operations in the Sankofa Fields.
The Court also ordered GNPC and the two ministries to file accounts of all payments they have made to Eni and Vitol since the day of service on them of the pending application for an order of payment of money due and owing to the defendants.
This is to be carried out within 21 days beginning from July 15 2022 and filed with the Court’s Registrar.
Meanwhile, the Court noted that the reliefs sought by Springfield were both prohibitive and mandatory injunctions, having demonstrated that it had a ruling for preservation in its favour which had not been stayed for purposes of execution.
This means there is therefore a subsisting court order which has the right to enforce and or protect through the process of law.
The trial Judge further noted that the Applicant (Springfield) had sufficiently demonstrated to the satisfaction of the court that there was a legal right worthy of the Court’s protection.
“The application is, therefore, neither frivolous nor vexatious as there are serious questions that ought to be determined in the pending application”. it added.
In the opinion of the Court, Springfield had demonstrated that despite the order of interim preservation that was obtained against ENI and Vitol, they had, through the filing of various applications in various courts frustrated the compliance and execution of the order of interim preservation.
"As if that is not enough, the resources which are alleged to be jointly owned by the Applicant and the Respondents are being dissipated by the Respondents on the blind side of the Applicant. The Respondents are further receiving payments monthly from third parties without accounting for same to the Applicant nor the Court,” the ruling further noted.
In 2020, the Government of Ghana declared the Sankofa Field and Afina Well unitized through the Minister of Energy and directed ENI and Springfield to commence the exchange of data with the view to unitizing the two areas to ensure optimization of the resource.
Since the directive, the two companies have failed to agree on the way forward.
Whereas ENI rejects the idea saying it was a rushed decision, Springfield has been in court for the law to be enforced to the letter in line with the Petroleum laws of the country.
See a copy of the ruling below: